TSH awarded engineering design and
contract administration services for the expansion of
the Bradford Water Pollution Control Plant
TSH was awarded the engineering design
and contract administration services for the expansion
of the Bradford Water Pollution Control Plant in the
Town of Bradford-West Gwillimbury. This project includes
a new extended aeration activated sludge plant with
tertiary treatment to increase the overall plant capacity
to 17,500 m per day. The design of the plant has started,
with a construction contract tendering date in February
2006. Construction is expected to take 70 weeks for
Phase 1 and an additional 12 weeks for Phase 2, with
an estimated plant start-up date of May 2007.
|